Iberdrola España invests €12 million in the modernisation of the Santo Estevo power station (Ourense) and reinforces its commitment to Galician industry

  • The plan launched by the company for the comprehensive refurbishment of the complex will enable the company to overhaul the four generating units in turn to extend their service life, incorporate technological advances and ensure their reliability
  • The first phase, which is already underway, has begun with the dismantling of the components and the rotor of unit 2, a component weighing approximately 250 tonnes and that has required a high-precision operation
Iberdrola technicians inspect power generation equipment inside a hydroelectric power plant.

The programme is scheduled to be completed in 2031, with a budget of €12 million.

Iberdrola España has begun a new cycle of comprehensive refurbishment of the Santo Estevo hydroelectric power station, located in the municipality of Nogueira de Ramuín in Ourense. The work has begun with the dismantling of the components and the rotor of unit 2, a component weighing approximately 250 tonnes, the removal of which required the use of two specialised cranes and a highly complex manoeuvre that took three hours to complete.


This work constitutes the first phase of a modernisation programme that involves the successive refurbishment of the four generating units. The programme is scheduled to be completed in 2031, with a budget of €12 million. The refurbishment of Unit 2 is expected to take one year and will account for €3 million of the total investment. The aim is to extend its service life, maintain the plant's operational reliability and performance and adapt its systems to the latest technological advances.


To carry out this work, Iberdrola has conducted preliminary technical studies to assess the condition of the equipment and plan the interventions. Iberdrola España operates several hydroelectric power stations in the River Sil catchment area. Together, these facilities have an installed capacity of 1,582 megawatts, equivalent to 45% of hydroelectric generation in the Galicia region. Their average annual output stands at 3,000 gigawatt-hours, approximately 50% of the region's average hydroelectric production.

Collaboration with Galician companies on the modernisation of the Santo Estevo power station

Iberdrola España is working in partnership with Galician companies on these projects, thereby boosting skilled employment and industrial activity in the region. Carrying out this work requires a significant deployment of specialist staff for maintenance, repair, assembly and machining tasks, which are essential for commissioning the equipment.


Among the Galician firms taking part in this supply chain are MILSA Trillo Galicia, Metalúrgica Gallega, Acebrón, Teiga TMI, Técnica 4, Montega, Tecdesoft, AIMEN, CEASA and CEFER, among others. All of them collaborate with the electricity company at other power stations, both within and outside Galicia. Their involvement helps to bolster activity within the ancillary industry.


Over the last five years, Iberdrola España at Generación Sil placed orders with Galician suppliers totalling €19.2 million, spread across 705 orders. Across the hydroelectric business as a whole, the figure amounted to €75.2 million, corresponding to 948 orders. In total, more than €94 million.


Each year, Iberdrola España's hydroelectric infrastructure on the River Sil generates more than €15 million in capital expenditure (Capex) and operating expenditure (Opex) and contributes a further €10 million in taxes to local and regional authorities — figures that do not include the 7% electricity tax.

Boosting employment in Galicia

Iberdrola España's power stations in Galicia generate more than 150 direct jobs in the Sil region, in addition to the indirect jobs associated with the system and its supplier companies. This involves a skilled workforce linked to the operation and maintenance of the facilities in the area, whose activity helps to sustain the local business fabric in the inland areas of Galicia. The Sil Unit is also responsible for operations within the Tamega system (Portugal), notably the Gouvaes pumped-storage power station, as an integrated organisation.


The Santo Estevo project began in 1945 with the opening of access routes through the Sil Gorge. Around 2,000 people worked on the construction, which involved 150,000 tonnes of cement and 10,000 tonnes of steel. Following its inauguration in 1956, it became the facility with the highest installed capacity in Europe at the time. 


Since then, the complex has undergone successive upgrades. In 2008 the company began expansion works involving a new underground cavern. San Esteban II came into operation in May 2013, bringing the complex's total capacity to 451 megawatts. On 1 January 2017, the San Pedro II underground power station came on stream; it acts as a counter-reservoir to regulate the flow of the River Sil, optimise power generation and contribute to navigability and tourism in the Ribeira Sacra.