News
05/03/2026

JV between bp and Iberdrola España has reached the final phase of construction of what will be the largest green hydrogen plant in Spain

  • The plant has reached 90% completion of its assembly phase and has 100% of the equipment on site.
  • Commissioning period will begin in May 2026
Four professionals wearing helmets and high-visibility vests pose at an industrial plant on a rainy day. Behind them is a building displaying the bp and Iberdrola logos, along with large tanks and industrial structures, in a facility linked to energy projects.

Visit to Iberdrola España and bp's green hydrogen plant in Castellón